This paper outlines the creation of a simulation model used to extrapolate duration and resource requirements needed for the construction of bridges based on a sampling of data obtained during a field research conducted on the construction process of a single bridge. A sampling of statistical data was taken during a field investigation to measure schedule and resource requirements (labor, raw materials and machinery) at various stages of a bridge construction project. This data was used to identify the probability distribution and the associated parameters for the project examined, and a simulation model was built to extrapolate the necessary schedule and resource requirements needed for various stages of similar bridge projects based on ThreePoint Estimation Method of Program Evaluation and Review Technique (PERT) and Monte Carlo Method. This simulation model’s resultant data for every process in an applicable construction project can be aggregated to form overall project duration and resource requirement statistical distribution using the Critical Path Method (CPM). The whole construction process will be visualized by a 4-dimensional (4D) model of the project which is created by appending time and resource requirements and to the 3-dimensional (3D) model that is built using the Building Information Modeling (BIM) and Alternativa 3D technology. Based on the simulation results of every procedure’s duration and resource requirements, the Network Program Diagram and Gantt Chart can be drawn Manuscript received February 20, 2014; accepted April 30, 2014 Wei-Dong Wang( ) Department of Civil Engineering, Central South University, Changsha 410075, China Email: 147745@163.com Jie Wu National Engineering Laboratory for High Speed Rail Construction, Changsha 410075, China Kai-Jun Wang The Third Railway Survey and Design Institute Group Corporation, Tianjin 300142, China Xin Wen Costing Department of Economic Planning Institute of the Ministry of Railways, Beijing 100038, China with Flex and ActionScript language. Furthermore, with the Network Program Diagram at the core, the 4D model can incorporate simulation’s resultant data with respect to total time and cost of the project to show the condition of resource requirements and the project’s progressing at any time.