Abstract

Road buildings projects are unique for their typical aspects. These typical aspects are the long-term preparation process (app. 16 years) and the construction phase (app. 4 years). Construction of the road building influences a large area in the country and has a big impact on the environment. Construction road building projects very often suffer from project delays and increasing budget because of many causes. Paper analyses process of obtaining information and other conditions for realization of the road-building projects. This paper describes the main road building project actors and main time schedule delays. After that, the process is analyzed and necessary information are identified. Finally, other necessary conditions for realization process are identified. Realization of the road-building process diagram (focused on documentation) was created and verbally evaluated.