Abstract

A generic, modular simulation model was constructed using the SLAM II discrete event modeling language to investigate the flowtime performance of a job shop. The findings of earlier research using conventional scheduling heuristics were confirmed and used to validate the design of revised AWINQ and MST heuristics. These heuristics were reformulated to take into account the state of the entire job shop at each rescheduling opportunity. Simulation results indicate that the revised heuristics perform better than the conventional SPT heuristic when job load is moderate. At high loads, the SPT rule was the preferred heuristic.

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.