Abstract
Most of the existing pipe string discharge devices in China are suitable for drilling operations, but some auxiliary devices for surface pipe string discharge in workover operations are not mature enough, and there are some problems such as inconvenient transportation, complex structure and large area. Based on the actual situation of small workover operation site, this paper puts forward the scheme of all-electric discharge device for well site operation pipe string, determines the structure function and work flow of the discharge device, carries out structural design for three parts of the lift, conveying device and pipe rack, and analyzes and calculates the structural parameters of the device. Through the static analysis of the main force components, the rationality of the device design is verified, and its structural strength is in line with the safe range.