Abstract

The Last PlannerSystem (LPS) has been implemented on construction projects to increase work flow reliability, a precondition for project performance againstproductivity and progress targets. The LPS encompasses four tiers of planning processes:master scheduling, phase scheduling, lookahead planning, and commitment / weeklywork planning. This research highlights deficiencies in the current implementation of LPS including poor lookahead planning which results in poor linkage between weeklywork plans and the master schedule. This poor linkage undetermines the ability of theweekly work planning process to select for execution tasks that are critical to projectsuccess. As a result, percent plan complete (PPC) becomes a weak indicator of project progress. The purpose of this research is to improve lookahead planning (the bridgebetween weekly work planning and master scheduling), improve PPC, and improve theselection of tasks that are critical to project success by increasing the link betweenShould, Can, Will, and Did (components of the LPS), thereby rendering PPC a betterindicator of project progress. The research employs the case study research method to describe deficiencies inthe current implementation of the LPS and suggest guidelines for a better application ofLPS in general and lookahead planning in particular. It then introduces an analyticalsimulation model to analyze the lookahead planning process. This is done by examining the impact on PPC of increasing two lookahead planning performance metrics: tasksanticipated (TA) and tasks made ready (TMR). Finally, the research investigates theimportance of the lookahead planning functions: identification and removal ofconstraints, task breakdown, and operations design.The research findings confirm the positive impact of improving lookaheadplanning (i.e., TA and TMR) on PPC. It also recognizes the need to perform lookaheadplanning differently for three types of work involving different levels of uncertainty:stable work, medium uncertainty work, and highly emergent work.The research confirms the LPS rules for practice and specifically the need to planin greater detail as time gets closer to performing the work. It highlights the role of LPSas a production system that incorporates deliberate planning (predetermined andoptimized) and situated planning (flexible and adaptive). Finally, the research presents recommendations for production planningimprovements in three areas: process related, (suggesting guidelines for practice),technical, (highlighting issues with current software programs and advocating theinclusion of collaborative planning capability), and organizational improvements(suggesting transitional steps when applying the LPS).

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.