A two-unit standby system is considered under excess time stochastic behaviour, i.e. the failure and repair time of the on line (off line) unit is exceeding some prespecified value. Whenever an operating unit crosses a prespecified operation time, it is sent to preventive maintenance and when repair of a failed unit crosses a prespecified time, the unit is rejected and replaced by a new unit. Using the regeneration point technique, certain characteristics of the system are derived and the cost of the system is calculated. Particular cases of the system are also considered.
Read full abstract