The transient processes in a 20 kV network due to single-phase short circuit fault in the 220 kV lines of a 220/20 kV supply substation are considered. Combinations of parameters at which overvoltages are the highest are determined. The overvoltages limited by surge arresters installed on 20 kV busbars are estimated.

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.