Abstract

In decision analysis, expected utility of discounted cash flows is the traditional approach to incorporate risk aversion into the evaluation of a project. The choice of discount rate as well as the convergence with the beta-adjusted approach from finance have always been in question. To address this gap, we adopt a risk-sharing setup in which investors have both treasuries and the stock market as alternatives to the project. For a full utility analysis of all the investor’s capital, we provide a unique discount rate that allows setting the horizon at the termination of the project. For a traditional analyst who conducts expected utility of discounted cash flows and ignores the capital not allocated to the project, we recommend an adjusted discount rate that compensates for double-counting the systematic risk.