Abstract

According to the regulation of Coal energy saving and emission reduction upgrade, transformation plan action (2014-2020) in China, aiming at the severe situation of the national energy conservation and emission reduction. We did a unit steam blowing for a power plant which has did a high efficient subcritical parameter rehabilitation. We did a detailed program for the unit steam blowing, overcome the small space for the temporary system pipe. With the strict control of the boiler operating parameters, we successfully complete the unit steam blowing work and fully guarantee the quality.