Abstract

The construction of AP1000 Nuclear Power Plant (NPP) has commenced in China. The AP1000 NPP features a passive design concept and modular construction technology. Based on the management of the construction of current AP1000 NNP, this paper describes the effects on Nuclear Island (NI) construction project management resulting from modular construction technology, as well as new construction techniques and methods. This paper puts forward new requirements for construction schedule management of the nuclear island construction at different levels. The AP1000 NI construction logic features the parallel construction of civil and structural erection as the main approach, with the integrated schedule of module fabrication, assembly and installation as support.