Abstract

The manufacturing line of the ITER Correction Coils (CC) at ASIPP in Hefei (China) was completed in 2013 and the manufacturing line of the ITER Central Solenoid (CS) modules is under installation at General Atomic premises in Poway (USA). In both cases, before starting production of the first coils, qualification of the manufacturing procedures is achieved by the construction of a set of mock-ups and prototypes to demonstrate that design requirements defined by the ITER Organization are effectively met. For each qualification item, the corresponding mock-ups are presented with the tests to be performed and the related acceptance criteria. The first qualification results are discussed.