Abstract

The Siam Photon Project promoted at the Siam Photon Laboratory is progressing slowly but steadily. The construction of the laboratory building was completed and the installation of the accelerator complex, that is the modified SORTEC machines from Tsukuba, is now under way. The first stage of the synchrotron assembly has been completed recently. The installation of the injector linac is about to be started. The construction of the additional magnet system, the new machine control system and the new vacuum chambers have been completed. The construction of the first beam line with photoemission experimental stations as well as that for the electron beam monitor will start soon. The design work for an undulator will also start soon. Some problems found in the case of the utilization of a second hand system are described.