Abstract

In the Resource–Constrained Multi–Project Scheduling (RCMPS) literature, studies on scheduling involving the minimisation of the maximum tardiness of multiple projects are rather limited. This paper, therefore, analyses the performance of the existing and newly proposed scheduling rules in the static RCMPS environment by considering performance measures involving Mean Tardiness (MT) and the Maximum Tardiness (MaxT) of projects. The present work evaluates scheduling rules that consider project due–dates, operation/activity duration times, operation/activity due–dates, project slack and activity slack, and presents the results of performance evaluation.

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.