Abstract

ABSTRACTAlthough some scheduling optimization models can be found in the literature, few of them include material flow and the resulting dilution. In this paper, a 3D mixing methodology is proposed to be incorporated into the production schedule model. To capture horizontal and vertical mixing, different scenarios are generated based on the particles that fall into a 3D cone of movement, CoM. The proposed model is a block caving scheduling optimizer, BCSO, which includes mixing in the optimization. The BCSO was tested on a real-case block caving mine with 424 drawpoints; also, a number of production schedules were generated for the same mine using PCBC GEOVIA software. Resulting production schedules show that the BCSO can improve the NPV of the project by 2% to 4% compared to the best case generated by PCBC.