Abstract

Variation Orders is often a reason for construction projects exceeding projects budget and delays; it is a global problem, particularly intensive in the case of a recession of the local economy and stagnation. In Iraq, all the projects have delays in completion, and the cost affects because of the variation orders, which are not well managed. The objective of this study was to identify the key causes responsible for the variation order in construction projects in Iraq using the system dynamic. System's dynamics is the discipline of academics and rooted initially been in management and the engineering sciences. The data relating to the performance of construction projects from 27 projects adopted by Diyala University were collected. Personal interviews and questionnaires survey to the selected projects of specialized engineers were done. The results revealed that the size of variation orders in Iraqi construction projects was high, and 13 key causative factors led to variation orders. The variation in cost was the most influential factor effecting the construction project in Iraq. When variation orders in a cost increased, the owner's opinion decreased. When the external factors increased, cost variation orders increased. It was concluded that minimizing the variation orders was very important to realize the cost in the construction projects. Therefore, the authority management and project managers must make a plan to address these key causes in future projects to ensure their success

Highlights

  • Variation Order (VO) is a common phenomenon in construction projects

  • The answers were based on the work sector of the academic degree, workplace, group specialty, years of work experience, and engineering field specialties were given in figures (2-6), respectively

  • Based on the investigations done in this study, the following conclusion can be drawn: 1. It was found that most of the variation orders were of the malicious type increased the cost due to the owner's requirements, and a little of it was used to improve quality

Read more

Summary

Introduction

Variation Order (VO) is a common phenomenon in construction projects. It involves an amendment of the original scope of work as in the contract [1]. Variations often cause disputes and dissatisfactions among the parties involved in construction projects. It is imperative to control VOs in a construction project [2]. 2020, identified the causes of VO as lack of materials and equipment spare parts due to closure, change in design by a consultant, lack of consultant's knowledge of available materials, errors and omission in design, conflicts between contract documents, owner's financial problems, lack of coordination among project parties, using the inadequate. 2018, suggested that consultants should understand the overall scope and goals of the project. The consultant's feeling of superiority over the contractor may prevent the consultant from

Objectives
Methods
Results
Conclusion
Full Text
Paper version not known

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.