Abstract

The excavation of adjacent pits following the initial foundation pit excavation can significantly influence ground settlement. Using a foundation pit excavation project in Changzhou as a prototype, this study employed the numerical simulation method in conjunction with the HSS model to analyze the settlement deformation characteristics of the original excavation and compare them with the recorded monitoring values. In this study, the analysis focused on the ground settlement between two pits by varying the spacing between them at different excavation depths. The findings revealed that the ground settlement does not exhibit a significant increase when the new pit is excavated at a shallow depth. However, it rapidly increases when the excavation depth of the new pit surpasses that of the existing pit. Furthermore, an increase in the distance between the two pits causes the maximum settlement position to shift towards the edge of the new pit. The maximum ground settlement is found to have a linear relationship with both the maximum horizontal displacement of the two pits and the spacing between them.

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.