Abstract
In this study, Hybrid Renewable Power System (HRPS) has been designed to meet the energy requirement of Istanbul Gedik University Vocational School (IGUVS) in an optimum way. The energy requirement will be achieved mainly with wind and solar power generation system. The hybrid regenerative power system will be requested from the network when it can’t meet its energy needs. The optimum configuration of grid-connected solar/wind hybrid power generation system will be determined by considering the wind speed data and solar radiation data of the location of IGUVS. Moreover, sensitivity analysis will be carried out taking into consideration the wind speed and solar radiation values. If the optimum hybrid power generation system specified is used, the carbon emission values obtained will be examined.
Highlights
TODAY, the production and consumption of energy have become a global problem worldwide, which is an independent problem that every country is experiencing.https://orcid.org/ 0000-0001-9695-886X https://orcid.org/0000-0001-6739-7717https://orcid.org/ 0000-0003-1632-8900https://orcid.org/0000-0003-4831-9005Manuscript received August 12, 2019; accepted October 16, 2019
It is the evaluation of which hybrid system is more optimal from alternative hybrid power generation systems when the wind speed values change between 2.67 m/s and 5.5 m/s and the solar radiation values change between 3 kWh/m2/d and 5.5 kWh/m2/d
As a result of optimization performed considering the optimum values of wind speed and solar radiation data for Gedik Vocational School, unit energy cost is calculated as http://dergipark.gov.tr/bajece
Summary
TODAY, the production and consumption of energy have become a global problem worldwide, which is an independent problem that every country is experiencing. Due to factors such as the depletion of conventional energy sources in recent years, the generation of carbon emissions from these sources and the emission of greenhouse gases, countries have begun searching for alternatives to meet their energy needs When countries plan their energy policies, they are mainly concerned with two critical parameters [1,2,3]. Each building must be transformed into an active structure that can produce its own energy, instead of being a passive energy consumer [9] As it is well known, the biggest handicap of renewable energy sources is the lack of continuity. The transfer of excess of the generated electricity to the interconnection network with auxiliary technical equipment provides economical benefits to both the producers and the countries
Talk to us
Join us for a 30 min session where you can share your feedback and ask us any queries you have
More From: Balkan Journal of Electrical and Computer Engineering
Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.