Abstract

AbstractBackgroundSimulation is a proven technique for effective construction site layout planning and heavy equipment resource optimization. Traditional simulation uses historical data as input for task durations. Data is fed into activity cycle diagrams which many times do not consider any of the rapidly changing spatial constraints that are present on a construction site. Very little research has been conducted towards more realistic, real-time simulation involving data gathering from live actors and documenting the effect of potential changes to such a spatial-temporal work environment.MethodsCell-based simulation, incorporating continuous spatial changes to the site layout during project operations and real-time Global Positioning System (GPS) location tracking data from equipment resources, is introduced for more realistic and rapid modeling. The potential of analyzing and visualizing the effects of spatial consideration of varying resource combinations in earthmoving cycles on productivity and site congestion are explored. It provides insight and awareness in decision making for resource management, site layout and internal traffic control planning.ResultsThe proposed cell-based simulation system handles complex and more realistic scenarios. Various cell parameters were tested in a case study of common earthmoving operations. The advantages of the cell-based over a traditional simulation model include ease of visualization and simplicity in modeling spatial constraints (e.g., ramp restricting traffic to one-way flow). The system provides full control over the flow of resources by using predefined rules or algorithms. It simplifies the design process since, except for some certain key cells, other ordinary cells followed the same rules without being programmed individually. Future research may involve multiple, non-interacting crews competing for resources and study of time-space conflicts in more detail.ConclusionsThe presented cell-based simulation system is able to model and visualize the cyclic activities of earthmoving equipment that occur on a construction site in greater detail than previous simulation methods have done. Using near real-time location data from equipment as input value in the simulation helps construction site project engineers, planners, and managers to improve coordination and monitoring of such construction resources.

Highlights

  • Simulating earthmoving operations is a classic example of simulation in construction engineering and management

  • State and Resource Based Simulation of Construction Processes (STROBOSCOPE), developed by Martinez (1996), represents a newer generation system for construction simulation based on Activity Cycle Diagrams (ACDs)

  • Simulation system The developed simulation system consists of three interacting components: the input, the simulation engine, and the output

Read more

Summary

Introduction

Simulating earthmoving operations is a classic example of simulation in construction engineering and management. They provide platforms for the graphical representation of operations, animations, and statistical tools for input and output data Templates in these systems provide a user-friendly environment, for example, the different construction operations exist as blocks for building new simulation systems. Even non-simulation experts comprehend the functionality of these systems These systems do not consider spatial constraints or spatial interactions among resources, which can be a crucial factor in resource optimization. To resolve these shortcomings, Kamat and Martinez (2001) created a system that coupled ACD-based simulation results with 3D visualization for the purpose of detecting potential operational risks. Some basic spatial reference was introduced into the simulation, the system cannot handle space-optimization problems

Objectives
Methods
Results
Conclusion

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.