Abstract
Taking the foundation settlement accident of a large heating boiler foundation in a city in collapsible loess area as an example, controllable splitting grouting can be achieved by controlling the grouting pressure, grouting pipe opening form, grouting volume and grouting method etc., so as to stabilize foundation settlement and improve foundation bearing capacity, for the boiler with large uneven settlement, for boilers with large uneven settlement, quicklime piles are used to jack up the foundation after splitting grouting to stabilize the foundation, the foundation is lifted with quicklime piles after splitting grouting to stabilize the foundation. The results show that the grouting amount of soil is within the design range, the grout splits in the soil several times to form a slurry vein, the settlement is stable after boiler reinforcement, the quicklime method can jack up the foundation and reduce the uneven settlement of the foundation, and the use of controllable splitting grouting can basically eliminate the slight collapsibility grade loess, which provides a new idea for solving the similar problem of uneven settlement of collapsible loess foundation buildings.
Published Version
Talk to us
Join us for a 30 min session where you can share your feedback and ask us any queries you have