Abstract

The construction of construction projects in Kupang district is currently experiencing a very rapid development, many buildings and roads were built to accommodate the needs of the community. This research focuses on the factors that cause delays that occur in the construction project of the Pancasila Flobamora Monument. This research was completed using a questionnaire distributed to parties directly involved in the process of building the Flobamora monument of the Pancasila house. The results of the study found 5 factors that have the highest importance index value, namely: lack of work experience of masons (68.41%), the influence of rainy weather (66.90%), late delivery of equipment to the project location (52.36%), lack of work experience. field supervisors (43.63%), late payments by the owner (32.29%). Recommendations given are based on the delay that occurred in the construction project of the Pancasila flobamora monument, namely the lack of work experience of masons, Increasing supervision of the masons by increasing the workforce of the head of workers and foremen. The influence of rainy weather, it is better if overtime hours are applied when the weather conditions are not raining so that reduced production due to rain can be overcome, the lack of work experience of field supervisors, providing assistance and direction for less experienced field supervisors.

Highlights

  • The construction of construction projects in Kupang district is currently experiencing a very rapid development, many buildings and roads were built to accommodate the needs of the community

  • This research focuses on the factors that cause delays that occur in the construction project of the Pancasila Flobamora Monument

  • This research was completed using a questionnaire distributed to parties directly involved in the process of building the Flobamora monument of the Pancasila house

Read more

Summary

KETERLAMBATAN PROYEK

Penelitian ini menitikberatkan pada faktor-faktor penyebab keterlambatan yang terjadi pada proyek pembangunan Monumen Flobamora Rumah Pancasila. Penelitian ini diselesaikan menggunakan kuisioner yang disebar kepada para pihak yang terlibat langsung dalam proses pembangunan monumen flobamora rumah Pancasila. Rekomendasi yang diberikan berdasarkan keterlambatan yang terjadi pada proyek pembangunan monumen flobamora rumah pancasila yakni kurangnya pengalaman kerja tukang, Meningkatkan pengawasan terhadap para tukang dengan menambah tenaga kepala pekerja dan mandor. Tujuan dari penelitian ini yakni mau mengetahui factor-faktor apa saja yang paling berpengaruh terhadap keterlambatan yang terjadi pada proyek pembangunan Monumen Flobamora Rumah Pancasila. Dimana dengan terlebih peneliti menyebar kuesioner kepada para pelaku yang terlibat dalam pembangunan Monumen Flobamora Rumah Pancasila antara lain para tukang, konsultan perencana, konsultan pengawas dan kontraktor.

Severity index
Importance index
ANALISIS DAN PEMBAHASAN
Terjadi perubahan desain oleh owner Kurangnya produktifitas peralatan
Saverity Index
Findings
Kekurangan bahan konstruksi Pengiriman bahan konstruksi yang terlambat