Abstract

The paper presents the assessment of technical condition of track on the example of two tram sections on Titov and Svyazistov streets in Novosibirsk. The authors have compared sections by the number of derailments and have revealed the main reasons of the derailments. As a result, they have established the volumes of maintenance of tram tracks and the required labour costs, as well as the works that make the main share of labour costs for 5 years on both considered sections. In order to control the track position for the provision of comfortable and safe transportation of passengers the authors recommend to use a track measuring truck.