ABSTRACT Bridges construction is one of the most challenging industries around the world as it necessitates a lot of experience, equipment and high budgets. Selection process of bridges’ structural system is mainly based on skill, knowledge base and experience that needs specified references helping in this process. There is a crucial need to manipulate a holistic Value e Engineering (VE) framework into the structural analysis/design of roadway bridges taking into consideration construction cost, construction time and environmental impacts. Unfortunately, the reported work on such an important field is still ecologically limited. The present research has two folds: (1) organize survey on VE related to structural-ecological prospective in bridge construction and (2) conduct a parametric study on analysis and design factors influencing VE outputs. For this purpose, a questionnaire was prepared to determine the extent of VE awareness among stakeholders and to test the controlling parameters. This survey has targeted a focus group of professional engineers in bridge engineering companies satisfying pre-determined characteristics. Setting the main VE parameters, study cases have been accounted for medium to large span simply supported and continuous roadway bridges with several cross sections using particular international code provisions. The VE included Embodied Carbon Emission (ECE) resulting from all activities thus estimating the cost of the carbon capture system. The total cost of each design case is estimated and compared to reach the minimum cost approach, thus enabling to recommend the most efficient structural system for Roadway Bridge. Hence, filling the gap between previous researches and bridge engineering practice.

Highlights

  • Value analysis was introduced into style by the US military around 1963 and its accommodation led it to be taken up by other agencies and departments [1]

  • Value engineering studies typically cost between 0.10% and 0.30% of the total project costs but availability 3% to 5% of the total costs [3]

  • Value engineering is usually applied during the project design develop­ ment cycle, to gain the greatest benefit and resource savings, and the value engineering can apply more than once during the life of the project [4]

Read more

Summary

Introduction

Value analysis (the technique designed to improve value without touching function) was introduced into style by the US military around 1963 and its accommodation led it to be taken up by other agencies and departments [1]. Value engineering studies typically cost between 0.10% and 0.30% of the total project costs but availability 3% to 5% of the total costs [3]. Value engineering is usually applied during the project design develop­ ment cycle, to gain the greatest benefit and resource savings, and the value engineering can apply more than once during the life of the project [4]. Application of value engineering helps to get the bridge project started in the right direction, and the repeated function help to refine the project track based on the changing information [6,7,8].

Objectives
Methods
Results