Abstract

Korean offshore oil and gas (O&G) mega project contractors have recently suffered massive deficits due to the challenges and risks inherent to the offshore engineering, procurement, and construction (EPC) of megaprojects. This has resulted in frequent prolonged projects, schedule delay, and consequently significant cost overruns. Existing literature has identified one of the major causes of project delays to be the lack of adequate tools or techniques to diagnose the appropriateness and sufficiency of the contract deadline proposed by project owners prior to signing the contract in the bid. As such, this paper seeks to propose appropriate or correct project durations using the research methodology of text mining for bid documents. With the emergence of ‘big data’ research, text mining has become an acceptable research strategy, having already been utilized in various industries including medicine, legal, and securities. In this study the scope of work (SOW), as a main part of EPC contracts is analyzed using text mining processes in a sequence of pre-processing, structuring, and normalizing. Lessons learned, collected from 13 executed off shore EPC projects, are then used to reinforce the findings from said process. For this study, critical terms (CT), representing the root of past problems, are selected from the reports of lessons learned. The occurrence of the CT in the SOW are then counted and converted to a schedule delay risk index (SDRI) for the sample projects. The measured SDRI of each sample project are then correlated to the project’s actual schedule delay via regression analysis. The resultant regression model is entitled the schedule delay estimate model (SDEM) for this paper based on the case studies. Finally, the developed SDEM’s accuracy is validated through its use to predict schedule delays on recently executed projects with the findings being compared with actual schedule performance. This study found the relationship between the SDRI, frequency of CTs in the SOW, and delays to be represented by the regression formula. Through assessing its performance with respect to the 13th project, said formula was found to have an accuracy of 81%. As can be seen, this study found that more CTs in the SOW leads to a higher tendency for a schedule delay. Therefore, a higher project SDRI implies that there are more issues on projects which required more time to resolve them. While the low number of projects used to develop the model reduces its generalizability, the text mining research methodology used to quantitatively estimate project schedule delay can be generalized and applied to other industries where contractual documents and information regarding lessons learned are available.

Highlights

  • According Korea Energy EconomicsInstitute offshore projects have been selectedAccording to to thetheInstitute [1],[1], offshore projects have been selected as as a a solution to end the stagnation of the shipbuilding industry caused by the poor business performance of solution to end the stagnation of the shipbuilding industry caused by the poor business thethe global economic crisiscrisis in 2008.these projects have recorded of the theshipping shippingindustry industrysince since global economic in 2008.these projects have massivemassive deficitsdeficits equating to a major of the domestic shipbuilding industry as a whole.recorded equating to a restructuring major restructuring of the domestic shipbuilding industry as In the

  • Before starting the regression analysis to correlate schedule delay risk index (SDRI) score and SD, it is worthwhile to mention some trend of schedule delay summarized in Table 10 below

  • The authors collected the contractual scope of work (SOW) documents from thirteen projects, and interviewed subject matter experts based on lessons learned of each project to identify the impactful words or phrases likely to be included in said SOW

Read more

Summary

Introduction

According Korea Energy EconomicsAccording to to thetheInstitute [1],[1], offshore projects have been selected as as a a solution to end the stagnation of the shipbuilding industry caused by the poor business performance of solution to end the stagnation of the shipbuilding industry caused by the poor business thethe global economic crisiscrisis in 2008.these projects have recorded of the theshipping shippingindustry industrysince since global economic in 2008.these projects have massivemassive deficitsdeficits equating to a major of the domestic shipbuilding industry as a whole.recorded equating to a restructuring major restructuring of the domestic shipbuilding industry as In the. Institute [1],[1], offshore projects have been selected as as a a solution to end the stagnation of the shipbuilding industry caused by the poor business performance of solution to end the stagnation of the shipbuilding industry caused by the poor business thethe global economic crisiscrisis in 2008 These projects have recorded of the theshipping shippingindustry industrysince since global economic in 2008. These projects have massivemassive deficitsdeficits equating to a major of the domestic shipbuilding industry as a whole. Recorded equating to a restructuring major restructuring of the domestic shipbuilding industry as In the

Objectives
Methods
Results
Conclusion
Full Text
Published version (Free)

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call