Abstract

We breakdown complex projects into activities and their logical dependencies. We estimate the project finish time based on the activity durations and relations. However, adverse events trigger delay cascades shifting the finish time. Here I derive a tropical algebraic equationfor the finish time of activity networks, encapsulating the principle of linear superposition of exogenous perturbations in the tropical sense. From the tropical algebraic equationI derive the finish time distribution with explicit reference to the distribution of exogenous delays and the network topology and geometry.