Abstract
This article presents the results of an analysis performed in order to determine the feasibility of integrating the generation of wind power plants into the electric power system of the Republic of Croatia and their connection to the existing transmission network, for the purpose of providing a basis for the HEP Transmission System Operator (HEP Operator prijenosnog sustava d.o.o.) to establish the upper limits for the construction of wind power plants of 360 MW, which the system is currently capable of integrating.
Talk to us
Join us for a 30 min session where you can share your feedback and ask us any queries you have
Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.