Abstract

Ever greater rated wind turbine generators (WTGs) are reaching their end of design life in the near future. In addition, first research approaches quantified the impact of long-term performance degradation of WTGs. As a consequence, this work is aimed at discussing and analysing the impact of upscaling and performance degradation on the economics of wind turbine lifetime extension. Findings reveal that the lifetime extension levelised cost of energy (LCOE2) of an 18 MW wind farm comprising of 0.5 MW rated WTGs are within the order of £23.52 per MWh. Alternatively, if the same wind farm consists of fewer 2 or 3 MW WTGs, the LCOE2 reduces to £16.56 or £15.49 per MWh, respectively. Further, findings reveal that an annual performance degradation of 1.6% (0.2%) increases LCOE2 by 34-41% (3.6-4.3%).

Highlights

  • Lifetime extension (LTE) is financially attractive in comparison to new investment and repowering due to the following identified root causes: the ageing of the current European wind fleet as illustrated in Figure 1; the more competitive allocation of onshore subsidies for new investments [1]; the trend of terminating repowering subsidies as observed in Germany, Spain, Denmark, and the UK [2]; the demonstration of competitive lifetime extension levelised cost of energy (LCOE2) [3]; and the comparatively little due diligence for the lifetime extension analysis (LTEA) as well as the hard-won, long-term stakeholder relationships with local communities

  • 3 Results 3.1 Upscaling Figure 6 presents LCOE2 estimates for an 18 MW wind farm consisting of different turbine size classifications for a 5-year lifetime extension period

  • It is expected that operators and owners will approach LTE from a more strategic point of view (+10-15 years vs. +5 years), especially for greater rated wind turbine generators (WTGs) (2–3 MW) with greater budgets to spend for the LTEA

Read more

Summary

Introduction

Lifetime extension (LTE) is financially attractive in comparison to new investment and repowering due to the following identified root causes: the ageing of the current European wind fleet as illustrated in Figure 1; the more competitive allocation of onshore subsidies for new investments [1]; the trend of terminating repowering subsidies as observed in Germany, Spain, Denmark, and the UK [2]; the demonstration of competitive lifetime extension levelised cost of energy (LCOE2) [3]; and the comparatively little due diligence for the lifetime extension analysis (LTEA) as well as the hard-won, long-term stakeholder relationships with local communities. In 2016, the distribution is predominantly composed of WTG below 0.5 MW and to a lesser impact of WTG in between 0.5 and 1 MW; this distribution is changing significantly over the decade with the pre-dominant WTG class shifting towards installations in between 0.5 and 1 MW. Given this observable trend of greater scale turbines reaching their end of design lifetime, this paper is aimed at analysing the development of lifetime extension LCOE with varying turbine classes.

Objectives
Methods
Results
Discussion
Conclusion

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.