Abstract

This study aims is to find the critical path which caused delay on the projects. Several factors which may affect to the delay are the weather, the lack of manpower, supply chain, equipment and so on. The research methodology was conducted to elaborate the causes are by using qualitative and quantitative researches. Over 35 respondents and 10 expert’s interviewee fill the questioner and were collected within two months. The result obtained is accelerated 3 paths from critical path method (CPM) then calculated the crashing program for each alternative. The alternative of acceleration applied are add the working hours in 4 (four) hours and 7 (seven) hours. In the end, the addition of 4 (four) hours could increase the workforce up to 25% of the total number of workers to get the value of accelerated finishing projects without ignoring the quality and quantity of them. Also, the additional labour is more beneficial in terms of costs they have relativity small number of working hours and would be more efficient.

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.