Abstract

One of the results of the network planning is a diagram that has identified critical path whose duration is equal to the project duration. For the purpose of the research in this paper, network diagram is observed with critical and subcritical paths and the influence of subcritical path on project duration is taken into the consideration. Superposition has been applied in order to define project duration, i.e. getting resulting — superponed path. Used methods are: analytical method — based on Clark's equations and numerical method – Monte Carlo simulation. Analytical method was basis for developing the project duration assessment model, which main characteristics are also presented in this paper.

Full Text
Published version (Free)

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call