Abstract

We study project scheduling so as to maximize the expected net present value when task durations are exponentially distributed. Based on the structural properties of an optimal solution we show that, even if preemption is allowed, it is not necessary to do so. Next to its managerial importance, this result also allows for a new algorithm which improves on the current state of the art with several orders of magnitude, both in CPU time and in memory usage.

Full Text
Paper version not known

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.