Abstract
AbstractThe San Francisco Hydroelectric Project in Ecuador is utilizing hydropower from the Rio Pastaza in a 230 MW plant. 8.4 km of the 11.2 km long HRT have been excavated by a double shield (DS) TBM. After 4,950 m TBM excavation in metamorphic rock series of the Cordillera Real, the TBM was trapped by a block failure of the rock under high water ingress and the TBM shield was demolished. A rescue programme was undertaken immediately on the TBM in order to stabilize the region of the event, to get control about the water ingress, to make free and to repair the TBM and to continue excavation under controlled conditions. Concurrently an alternative rescue programme was investigated and started in order not to waste time if the rescue of the TBM should fail or if further events should occur. The TBM stoppage lasted for about five month and the rescue programme enabled the repair of the TBM and a controlled restart of the TBM without any accident. After the restart the TBM again reached a sufficient daily progress of more than 20 m/d and the tunnel could be finalized with success.
Talk to us
Join us for a 30 min session where you can share your feedback and ask us any queries you have
Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.