Abstract

In this article, we deal with an integrated scheduling for unrelated parallel machines, batches, and heterogeneous delivery trucks. In a manufacturing plant, jobs ordered by customers are manufactured by one of several unrelated parallel machines. Then, they are grouped and delivered to the respective customers by heterogeneous trucks with different capacities and travel times. The objective of the problem is to simultaneously determine the machine schedule, batching, and truck-delivery schedule to minimize the make span of the entire process. To solve this problem, we derive a mathematical model to obtain the optimal solution, and we propose rule-based meta-heuristics using single-stage GA framework. Through randomly generated instance examples, the performances of the proposed meta-heuristics are compared.