Abstract

Based on the real-time settlement monitoring of embankment on-site, Hyperbola method and Index curve method are used in the prediction of embankment settlement and the prediction results were compared to verify the feasibility and the potential engineering value of the prediction of embankment settlement. The calculation results showed that the relative error of the results calculated by the above methods was controlled within 2%. The accuracy of early settlement prediction of Index curve method was lower than the accuracy of later settlement prediction, but the predicting result met the needs of the engineering accuracy. The accuracy of settlement prediction of Hyperbola method was significantly higher than Index curve method. Through the comparing and analyzing of the prediction results of embankment settlement, the final settlement value calculated by Hyperbola method was higher than the real-time monitoring on-site, and the final settlement value calculated by Index curve method was lower than the real-time monitoring on-site, Hyperbola method is more suitable for the estimation to the subsidence of actual embankment engineering construction.

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.