Abstract

Purpose The causes of high-speed railway failures are complex, and it is difficult to quantitatively and accurately describe safety evaluation. The purpose of this paper is to construct a model to ensure the safety of high-speed railway operations. Design/methodology/approach The authors construct a high-speed railway operation safety evaluation index system from four aspects: personnel, equipment, environment and management and analyze the inter-coupling relationship of various safety factors. Based on the evaluation index system, the use of network analytic hierarchy process (ANP) and fuzzy comprehensive evaluation will be used to establish a high-speed railway operation safety evaluation model. Findings Through the literature investigation and field investigation, combined with high-speed railway safety key points and system composition, 4 first-level indicators and 17 second-level indicators were selected to construct a high-speed railway operation safety evaluation index system. It can be seen from the results that the personnel management system and the signal and control system have the largest weight. Originality/value On the basis of establishing an evaluation index system, comprehensively considering the internal coupling relationship between evaluation indexes and the fuzziness of high-speed railway operation safety evaluation, high-speed railway uses ANP fuzzy network analysis method to construct high-speed railway operation, and the safety evaluation model has certain advantages and practicability in the case of the relative lack of high-speed railway operation data and fault data.

Highlights

  • As of the end of 2018, the mileage of China’s high-speed railways that have been built and put into operation reached more than 29,000 km, accounting for more than 66% of the world’s high-speed railway operating mileage

  • 2.1 Evaluation index analysis The factors affecting the safety of high-speed railway operations are analyzed from the four aspects of personnel, equipment, environment and management

  • Personnel factors refer to the staff of various functional departments such as train depot, locomotive depot, public works depot and electricity depot during the operation of high-speed railway, and include management personnel and technical operators at all levels, as well as passengers of high-speed rail trains

Read more

Summary

Introduction

As of the end of 2018, the mileage of China’s high-speed railways that have been built and put into operation reached more than 29,000 km, accounting for more than 66% of the world’s high-speed railway operating mileage. China’s high-speed railway construction has made world-renowned achievements, it still needs to be improved in terms. © Leyi Cheng, Yinghan Wang and Yichuan Pe. Published in Smart and Resilient Transport. The full terms of this licence maybe seen at http:// creativecommons.org/licences/by/4.0/legalcode

Objectives
Results
Conclusion
Full Text
Paper version not known

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.