Abstract

The pipe jacking method is widely used in water supply and drainage, power tunnels, vehicle tunnel construction, and other fields. The main challenges include friction resistance, axis deviation, and environmental disturbance, especially when large-diameter pipes are jacked along the curve underwater. Based on a large-diameter pipe jacking project under Jinshan Lake, this paper records the settlement of surrounding structures, the jacking force, and the deviation in the axis and elevation during the jacking process. Furthermore, the factors affecting the monitoring data under different working conditions are studied, and the key points are concluded. The outcomes of the study will provide a reference and serve as a guidance for future related projects.