Abstract

This paper presents an analysis of the appropriate size and installation position of a battery energy storage system (BESS) for reducing reverse power flow (RPF). The system focused on photovoltaic (PV) system power plants. The RPF from the distribution system into the transmission systems impacts the power system due to the increased penetration of the PV system, which produces more power than load. The analysis was divided into three parts: 1) Analysis of the initial load and capacity of the PV power plant; 2) Analysis of the initial load and the load when the capacity of the PV power plant is increased; 3) Analysis of the increased load and capacity of the PV power plant. The stability of the system for each position of the BESS guided the analysis of the reduction of the RPF according to two criteria: reducing the RPF directly and smoothing the distribution load curve. The analysis of the appropriate installation position of the BESS was compared at three positions: 1) at a 115-kV bus; 2) at a 22-kV bus; 3) at a PV power plant. The results of this research showed that the BESS can reduce the RPF and increase the smoothing of the distribution load curve. It can also reduce energy loss and maximum power consumption. However, the appropriate installation position of the BESS was in the PV power plant, because this reduced the energy loss, power fluctuations and electricity production more than installing the BESS at a 115-kV bus or a 22-kV bus.

Highlights

  • At present, the production of energy from renewable resources in Thailand is increasing because the government has announced several policies to promote the photovoltaic system (PV) system sector

  • This paper presents an analysis of the appropriate size and installation position of a Battery energy storage system (BESS) using the DigSILENT Power Factory program for the reduction of reverse power flow (RPF) in transmission systems

  • The analysis results show that a BESS can reduce the RPF and increase the smoothing of the distribution load curve

Read more

Summary

INTRODUCTION

The production of energy from renewable resources in Thailand is increasing because the government has announced several policies to promote the PV system sector. The reduction of the RPF and the smoothing of the distribution load curve were compared when the BESS was installed at the 115-kV high-side bus in the substation, at the 22-kV low-side bus in the substation, and in the PV power plant in the distribution system. The best BESS installation location is the PV power plant, since this reduces the energy loss the most, especially by smoothing the distribution load curve

REASONABLE COST ANALYSIS
Findings
CONCLUSION
Full Text
Paper version not known

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.