The roof of the underground garage of project A in Q city has been designed with waterproofing and drainage system of the planted roof. In the process of construction, there are some quality problems. Through the use of PDCA quality management cycle method, the quality problems are investigated and analyzed. And the corresponding plans, implementation of countermeasures, consolidation measures are made, so that the quality problems can be finally resolved to achieve the desired goal.

Highlights

  • As one of the 10 new technologies in the construction industry of the 2017 edition of the Ministry of Housing and Urban-Rural Construction, the planting roof is based on the top plane of the underground garage and has the functions of waterproof, drainage, water storage, green space and heat insulation

  • In the event of leakage, it is not appropriate to look for the causes of leakage

  • The underground garage building area is 5448.18 square meters, and the roof of the underground garage adopts planted roof. Both the common waterproof layer and the root resistant waterproof layer of the roof are made of self-adhesive polymer waterproof membrane, combined with rigid waterproof structure board, to form a rigid and flexible composite waterproof system

Read more

Summary

Introduction

As one of the 10 new technologies in the construction industry of the 2017 edition of the Ministry of Housing and Urban-Rural Construction, the planting roof is based on the top plane of the underground garage and has the functions of waterproof, drainage, water storage, green space and heat insulation. It can improve the urban ecological environment, alleviate the heat island effect, save energy and reduce emissions, and beautify the landscape. The design generally adopts structural waterproofing, membrane waterproofing, and combined waterproofing of seepage and drainage. The causes of leakage are related to the performance of building waterproofing, and related to the upper layer of soil cover, pouring mode, climate and other conditions [1,2,3]

Engineering profile
Causes analysis
Technical interaction
Roof concrete elevation control
Increase the smoothness and slope of HDPE drains
Construction standardization
Refinement of the construction process

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.