Abstract

Background:At the early phase of project development, highway engineering estimators seek to determine the duration of highway construction projects for the purpose of construction planning and administration. Thus, it is vital to study and analyze the estimation accuracy factors of highway construction project duration. In this regard, several studies have been conducted to identify and analyze the estimation accuracy factors of project duration in various ways to improve the estimation and management performance of all the contracting parties. However, very less effort has been devoted to evaluating the duration estimation accuracy factors in the case of the highway construction industry under fuzzy environment.Objective:This paper aims to analyze and prioritize the critical factors that potentially affect the duration estimation accuracy of the highway construction projects in Ethiopia under fuzzy environment.Methods:An extensive review and discussions with highway engineering experts were carried out to explore and identify the duration estimation accuracy factors. The study data collection process consists of two stages. The first stage is to conduct a questionnaire survey. Whereas, the second stage is to carry out the pair-wise comparison matrix to capture the imprecision and vagueness in subjective responses. Then, a λ-cut set method to reduce the initial list of factors and exploratory factor analysis was used to classify the reduced set of factors into smaller groups. Finally, a fuzzy hierarchy process algorithm with the use of triangular fuzzy numbers was presented for prioritizing critical factors.Results:A cut -off value, λ = 0.95, was verified which resulted in the identification of critical accuracy factors. Accordingly, 12 critical factors were opted and categorized as a cluster of similar items into 5 groups. Finally, the analytical results obtained from fuzzy AHP algorithm revealed that project complexity, project size, bridge type and complexity were found to be the four top-ranked factors based on the global priority weight.Conclusion:These factors must be a serious concern in estimating and administering the contract and the duration of highway construction projects at the early phases of project development so that the time deviation upon the completion of the project can be minimized.

Highlights

  • Establishing a realistic duration at the early stage of infrastructure projects is important for both contractors and clients

  • The analytical results obtained from fuzzy AHP algorithm revealed that project complexity, project size, bridge type and complexity were found to be the four top-ranked factors based on the global priority weight

  • This study demonstrates the application of fuzzy extent analysis and AHP in prioritizing and ranking the significant factors that affect the estimation accuracy of road construction project duration at the early phases in the project development under fuzzy environment

Read more

Summary

Introduction

Establishing a realistic duration at the early stage of infrastructure projects is important for both contractors and clients. An accurate determination of duration and cost at an early phase of project development can aid stakeholders to meet public expectations and avoid the public related problems about time overruns. It can be useful in the bid evaluation stage. In cases where bidders are requested to specify a construction period and cost, the expected project duration and cost can be used as one of the bid evaluation criteria. It is vital to study and analyze the estimation accuracy factors of highway construction project duration. Very less effort has been devoted to evaluating the duration estimation accuracy factors in the case of the highway construction industry under fuzzy environment

Methods
Results
Conclusion
Full Text
Paper version not known

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.