Abstract

The results of field tests on a buried, 34-inch diameter gas pipeline adjacent to a 525 kV ac power transmission line for 54 miles are discussed. Comparison is made between measured inductive coupling data and predictions obtained using the theory developed in part I of this paper. An excellent agreement of the predicted and measured results is shown for the location and magnitude of all induced voltage peaks on the pipeline.

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.