Abstract
Common power system restoration planning strategy is based on a ‘build up’ approach, where a blackout system is sectionalized among several islands for parallel restoration prior to resynchronization. In order to speed up the resynchronization of the islands, each island must have similar energizing times. However, there is a huge number of possible combinations of islands that can be formed. Thus, this paper proposes a method to determine optimal islands that have similar energizing times. The method involves identifying transmission lines that should not be connected to form the islands. The proposed method is based on the combination of heuristic and discrete optimization methods. The heuristic technique is proposed to find initial solution that is close to the optimal solution. This solution will guide the optimization technique, which is the discrete Artificial Bee Colony optimization method, to find the optimum solution. The proposed method also considers restoration constraints including black start generator availability, load-generation balance, and the maintenance of acceptable voltage magnitude within each island. The proposed method is validated via simulation using IEEE 39, 118-bus and 89-bus European systems. The advantage of the proposed method in terms of restoration time is demonstrated through a comparison with other literature.
Highlights
Several blackouts have occurred recently, such as the major disturbance in Western Europe in September 2003 [1], in northern India in July 2012 [2], in Pakistan in January 2015 [3], and the widespread power blackout in March 2015 in Turkey [4]
Considering the strength of the optimization method in finding the optimal solution and its flexibility incorporating multiple objectives and constraints, this paper proposes a combination of heuristic and optimization methods assisted by graph theory technique
The results show that the voltage at each bus in the optimal islands falls within 0.9 p.u. to 1.1 p.u
Summary
Several blackouts have occurred recently, such as the major disturbance in Western Europe in September 2003 [1], in northern India in July 2012 [2], in Pakistan in January 2015 [3], and the widespread power blackout in March 2015 in Turkey [4]. In order to minimize losses, the system needs to be restored as fast as possible This requires careful planning during the process of energizing individual power system components, such as generator units, transmission lines, substation buses, loads, and other facilities, back to normal. The islands formed should fulfill the power generation-load balance and voltage limit constraints.
Talk to us
Join us for a 30 min session where you can share your feedback and ask us any queries you have