Abstract

Production equipment that has a high operating time becomes a vital aspect in supporting the operational system, and its maintenance becomes a critical point that must be planned. This research discusses maintenance policies that focus on machine reliability and parts availability to produce proper maintenance actions, optimal maintenance scheduling and good spare-parts management. The research was conducted on a developing manufacturing company engaged the field of agricultural aids in the city of Bekasi. This study focused on hydraulic shear machines because they have the largest downtime value of 8,344.8 minutes. This problem has a negative impact on the company because it can reduce the yield. Based on these conditions, the study was conducted using the Reliability Centered Maintenance method to update the maintenance patterns and Poisson Process to determine the number of component requirements needed for the next one year. The data obtained in the form of historical damage to the machine, component cost, labor cost and production cost. This research produces an optimal preventive replacement time interval that is every 154 hours for the oil seal component, 242 hours for the shear blade component, and 324 hours for the oil hydraulic hose (1/2") component. While the number of critical components required for the next 1 year is 37 units for oil seal component, 10 units for shear blade components, and 7 units for oil hydraulic hose (1/2") component.

Highlights

  • Production equipment that has a high operating time becomes a vital aspect in supporting the operational system, and its maintenance becomes a critical point that must be planned

  • Perusahaan masih menerapkan run to failure maintenance pada sistem pemeliharaannya, di mana aksi dilakukan setelah mesin atau fasilitas produksi mengalami kegagalan atau kerusakan sehingga tidak dapat berfungsi dengan baik (Moubray, 2000)

  • Hasil penelitian ini memberikan rekomendasi kepada perusahaan sehingga pihak manajemennya dapat merencanakan dan menjadwalkan kegiatan pemeliharaan serta menentukan jumlah persediaan suku cadang tiap komponen kritis secara tepat

Read more

Summary

Introduction

Production equipment that has a high operating time becomes a vital aspect in supporting the operational system, and its maintenance becomes a critical point that must be planned. Berdasarkan hasil FMEA, terlihat komponen oil seal, shear blade dan oil hydraulic hose (1/2”) memiliki nilai RPN tinggi dan terpilih menjadi objek penelitian. Hasil perhitungan interval waktu penggantian pencegahan menunjukkan bahwa penggantian komponen dilakukan setelah pemakaian 154 jam untuk komponen oil seal, 242 jam untuk komponen shear blade dan 324 jam untuk komponen oil hydraulic hose (1/2”).

Results
Conclusion