Abstract

The construction of cafe and salon by PT DTD has been delayed in terms of time. The purpose of this study is to calculate the best time optimization and determine the critical path of the cafe and salon construction project at PT DTD. This research is an evaluation of a project that has been completed. The methods used are Critical Path Method (CPM) and Project Evaluation Review Technique (PERT). The software used is POM-QM for Windows. The project runs for 15 months or 62 weeks from the initial target of the contractor being 8 months. Using POM-QM, from the PERT method, the optimum time for the project is 50 weeks. Project optimization can be carried out using PERT and CPM methods with POM QM software.

Highlights

  • The construction project of a 3-storey cafe & salon building carried out by PT

  • Project optimization can be carried out using Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) methods with POM QM software

  • PERT is an acronym for Program Evaluation and Review Technique, the PERT technique is a method that aims to reduce delays and production disruptions as much as possible, as well as coordinate various parts of a job as a whole and speed up project completion. (Upadi, 2011)

Read more

Summary

Objectives

The purpose of this study is to calculate the best time optimization and determine the critical path of the cafe and salon construction project at PT DTD

Methods
Results
Conclusion

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.