Abstract

The smart grid with flexible topologies receives intensive attention recently. Transmission switching (TS) alters the power system topology during operation, and has been demonstrated for the advantage of economic and secure operation of power systems. TS includes a chain of sequential switching actions which bring disturbances to the system if the switching actions are not properly designed. Unfortunately, it is not considered or well-studied in existing works. In this paper, a new multi-period TS model that considers the transition security and a two-stage iterative method are proposed. In the TS model, we take into account the fact that only one line is permitted to switch up or down at a time and the security of each switching action is considered. The proposed iterative solution makes the TS model more tractable under AC framework. Case studies on a 6-bus system and the IEEE 57-bus test system have varified the effectiveness of the proposed model. Numerical results show that: ① the consideration of transition security of TS is essential; ② the transition path is directly related to secure and fast the transmission switching; ③ the proposed model and solution method give an effective way to determine the switching sequence and switching timing under transition security criteria.

Highlights

  • The branches and bus-bars of transmission network are characterized as fixed assets during system operation

  • The optimal security transition (OST) problem is a mixed integer non-linear programming (MINLP) problem

  • Nowadays the power system is facing more and more challenges due to the uncertainty and randomness brought by renewable energy resources

Read more

Summary

Introduction

The branches and bus-bars of transmission network are characterized as fixed assets during system operation. To manage the computational burden caused by discreteness and nonlinearity, the heuristic algorithms have been investigated to reduce the solution time, such as the space prescreening [25, 26], switchable branch ranking [27], Benders decomposition [14], and parallel computing [22, 28] While these existing studies acknowledge certain benefits of TS, researchers pay little attention to the security and optimality of the transition path from the initial network to the target one. The first stage is a traditional TS problem that determines the new network topology and the corresponding generation outputs based on specified objective regardless of the transition path and switching security.

Problem formulation
Decomposition strategy
Solution methodology
Master problem formulation
Sub-problem formulation
Six-bus system
IEEE 57-bus system
Conclusion
Full Text
Paper version not known

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.