Abstract

Although tremendous technological and strategic advances have been developed and implemented in the construction sector in recent years, there is substantial room for improvement in the areas of productivity growth, project performance, and schedule reliability. Thus, the present paper seeks to discover why the currently applied scheduling tools and the latest agile-based project organization approaches have not yet achieved their full potential. A missing interlinkage between the project’s design, cost, and time aspects within the project design phase and its sparse utilization throughout project execution were indicated as the driving contributors responsible for the slow progress in development. To fundamentally change this situation, an extensive and coherent project organization solution is proposed. The key process of this solution utilizes a 5D Building Information Model comprising tight concatenations between the individual model objects and the corresponding construction cost and time effort values. The key dates of a waterfall-based construction process simulation, set during the project planning phase, provide particular information to create a structure for agile organized project execution. The implementation of information feedback loops allows target/actual comparisons and contributes to continual improvements in future planning. A comparative case study was conducted with auspicious results on improvements in the overall project performance, and schedule and cost reliability.

Highlights

  • Large-scale construction projects are multi-faceted systems of complex and dynamic processes, which are constantly subjected to a multitude of internal and external influencing factors [1]

  • Since the current scientific literature does not provide a coherent solution that combines the advantages of the previously described methods and the unexploited possibilities, this paper presents a comprehensive approach to obtain these goals

  • Each construction section was completed on time, so each predetermined milestone passed on time

Read more

Summary

Introduction

Large-scale construction projects are multi-faceted systems of complex and dynamic processes, which are constantly subjected to a multitude of internal and external influencing factors [1]. The applied schedules often do not meet project-specific process requirements, frequently run out of time, and are exceeded or totally disregarded In this way, projects are considerably delayed, costs run out of control, and the failure of the project becomes foreseeable [2,3,4]. Doloi (2012), Braimah (2014), and Larsen (2016), in addition to many others, investigated the significant impediments that directly impacted the project’s schedule [13,23,24] The results of these studies indicated weak design elements; poor project planning, site management, and project control; insufficient contractor experience; contract payment problems; equipment availability; weather/environmental conditions; and material supply issues as the primary causes for project delays [13,23,24]. In order to further investigate and narrow down the described causes, current project management methods and the most recent solution approaches will be examined in the following

Current Common Project Management and Scheduling Approaches
The 5D-PROMPT Method
The Comparative Case Study
Results and Multi
Discussion and Conclusions
Future Perspective