Abstract

Longwall chock support failures seriously restrain the safety and high-efficiency of mining of extra thick coal seams, as well as causing a great waste of coal resources. During longwall top-coal caving (LTCC), the influential effect of the properties and the movement regulation of top-coal on strata behavior cannot be ignored, since the top-coal is the medium through which the load of the overlying strata is transferred to the chock supports. Taking Datong coalfield as an example, the mechanism of a chock support failure in the LTCC face was investigated. Research findings indicated that the hard top-coal and insufficient chock support capacity were primary reasons for chock support failure accidents. On account of the field-measured results, a new method to determine support capacity was proposed, which fully took the impact of the top-coal strength into consideration. The calculation revealed that the required support capacity had exceeded the existing production maximum, at about 22,000 KN. Since it was unrealistic to simply increase chock support capacity, other approaches, according to the theoretical analysis, were proposed, such as lowering the integrity and strength of the top-coal, and upgrading its crushing effect to weaken the support load effectively during the weighting period, which reduces the likelihood of chock support accidents occurring. Based on this, hydraulic fracturing for hard top-coal and optimization of the caving process (chock supports raised up and down repeatedly by manual operation before moving forward) were presented. The proposed solutions were successfully applied in LTCC-west8101 for subsequent mining and achieved substantial benefits. The above research provides valuable references and ideas for the control of strata behavior to ensure safe and highly efficient mining in extremely thick and hard coal seams with the LTCC method.

Highlights

  • Datong coalfield located in the northern Shanxi Province, China, is a typical two-hard coalfield [1]

  • The mechanism underlying the chock support failure accidents in the longwall top-coal caving (LTCC) working perspective, which fully took the impact of the top-coal strength into consideration

  • The research indicated that hard top-coal and insufficient chock support capacity were primary reasons for chock support failure accidents

Read more

Summary

Introduction

Datong coalfield located in the northern Shanxi Province, China, is a typical two-hard coalfield (i.e., hard roofs and hard coal seams) [1]. Some have attributed chock support failure to the instability of the according to this point of view, the instability of the overlying strata structure would occur periodically overlying strata structure [2,21,22], and the common preventive measure is to reduce the along the mining direction of working face most under such an invariable condition [22], resulting in mining height In this case, failure the loss of coal resources would be inevitable order totoensure safe massive chock support accidents with a regular distribution.

Case Study2
Mechanism ofof
The Insufficient Capacity of Chock Supports
TheBeing
Determination of Reasonable Support Capacity
Controlling
Hydraulic
Optimization of Caving Process
Engineering Implementation Effect
Conclusions
Full Text
Paper version not known

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.