Abstract

The technical and economic feasibility of photovoltaic (PV) power plants throughout their lifetime must be evaluated prior to their development and operation such that the sustainability of the project can be justified. This paper presents the Life Cycle Assessment (LCA) of energy and the LCA of economics for a 5 MW grid-connected photovoltaic (GCPV) power plant located in the East Coast of Malaysia. Firstly, an LCA of energy was conducted to evaluate the expected energy yield, energy payback period and energy return of investment throughout the project lifetime. Later, an LCA of economics was performed to determine several economic performance indicators such as the net present value, internal rate of return, payback period and return of investment.

Full Text
Paper version not known

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.