Superstructure of Zhuzhou Bridge in Baise is a combined system with strong beam and weak arch. It is combined by concrete arches of continuous rigid frame-steel tube. The construction sequence is first the beam then arch, finally the temporary pier is demolished to form the combined system. The middle three parts of steel tube arch rib in the middle span were assembled to a large unity, and it was integrally lifted by synchronous system of hoisting jack to reach positive stop. The techniques have the characteristics of fast, safe and low cost.