Karaikal Port Private Limited (KPPL) was a special purpose vehicle created by MARG Group on February 18, 2006 to develop Karaikal port. According to the concession agreement signed for a period of 30 years, KPPL was given rights to Karaikal port on a Build, Operate and Transfer (BOT) basis. It was to phase the building of the port based on short term, midterm and long term demand. By August 22, 2011, Phase I of construction had been completed, and Phase IIA was nearing completion. Though the project had not faced any major problems in its development, there were issues such as restrictions on the availability of land for any future expansion, limited scope of hinterland businesses, small scale environmental issues and others that needed to be addressed for the future development of the port.