Abstract

Electrical energy is critical to a country’s socioeconomic progress. Distribution system expansion planning addresses the services that must be installed for the distribution networks to meet the expected load need, while also meeting different operational and technical limitations. The incorporation of distributed generation sources (DGs) alters the operating characteristics of modern power systems, resulting in major economic and technical benefits, such as simplified distribution network expansion planning, lower power losses, and improved voltage profile. Thus, in this study, an analytical method is used to design the expansion planning of the Addis North distribution network considering the integration of optimal sizes of distributed generations for the projected demand growths. To evaluate the capability of the existing Addis North distribution network and its capability to supply reliable power considering future expansion, the load demand forecast for the years 2020–2030 is done using the least square method. The performance evaluation of the existing and the upgraded network considering the existing and forecasted load demand for the years 2030 is done using ETAP software. Accordingly, the results revealed that the existing networks cannot meet the existing load demand of the town, with major problems of increased power loss and a reduced voltage profile. To mitigate this problem, the Addis North feeder-1 distribution network is upgraded and for each study case, the balanced and positive sequence load flow analysis was executed and the maximum total real and reactive power losses were found at bus 29. The result shows that the upgraded network of bus 29 was the optimal location of DG and its size was 9.93 MW. After the optimal size of DG was placed at this bus, the real and reactive power losses of the upgraded networks were 0.2939 MW and 0.219 MVAr, respectively. At bus 29 the maximum power losses reduction and voltage profile improvements were found. The active and reactive power losses were minimized by 21.285% and 19.633% respectively and the voltage profiles were improved by 8.78%. Thus, in the predicted year 2030, DG power sources could cover 61.12% of the feeder-1 power requirements.

Highlights

  • Generation units, transmission, and sub-transmission networks, distribution systems, consumption centers, protection equipment, and control devices are all common elements of an electrical network [1]

  • This paper proposes a binary particle swarm optimization (PSO)-based heuristic evolutionary algorithm for solving single and multi-objective distribution system expansion planning problems, as well as distributed generation sources (DGs) and the traditional method

  • Reactive power planning and network reconfiguration are used in this paper to optimize DG penetration and reduce yearly DG losses while taking into account feeder capacity, short circuit level, and investment cost restrictions

Read more

Summary

Introduction

Generation units, transmission, and sub-transmission networks, distribution systems, consumption centers, protection equipment, and control devices are all common elements of an electrical network [1]. The fundamental goal of distribution network expansion planning (DNEP) is to offer consumers a dependable and cost-effective solution while providing constant voltages and power quality [2]. This aim is usually obtained by fortifying current infrastructure and substations or adding additional ones due to technical and operational restrictions [3,4]. Electricity is generated by large-scale power plants and transmitted to end-consumers via transmission and distribution networks in typical power networks. This is referred to as a centralized generation. Photovoltaic (PV) plants, micro-hydro plants, fuel cells, and energy storage devices, such as batteries are all examples of current DG technologies [6]

Related Work
System Modeling and Load Flow Analysis
Power Loss Calculation
Voltage Drop
Conductor Size Selection
Transformer Size Selection
Distributed Generation Sizing and Placement
Problem Formulation
Constraints
Identification of Location of DG
Forecasting of Peak Load
Result and Discussion
Existing Power Distribution System Assessment up to 2030
DG Integration on the Upgraded Existing Network
DG Impact on Voltage Profile
Findings
V: Load at 2030 with Upgraded Line parameters
Conclusions
Full Text
Published version (Free)

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call