Abstract

Engineering, Procurement, and Construction (EPC) of oil and gas megaprojects often experience cost overruns due to substantial schedule delays. One of the greatest causes of these overruns is the mismanagement of the project schedule, with the piping works (prefabrication and installation) occupying a majority of that schedule. As such, an effective methodology for scheduling, planning, and controlling of piping activities is essential for project success. To meet this need, this study used the Critical Chain Project Management (CCPM) to develop a piping construction delay prevention methodology, incorporating material procurement processes for EPC megaprojects. Recent studies indicate that the traditional scheduling method used on oil and gas mega projects has critical limitations regarding resource scarcity, calculation of activity duration, and dealing with uncertainties. To overcome these limitations, the Theory of Constraints-based CCPM was proposed and implemented to provide schedule buffers management. Nonexistent in literature, and of critical importance, is this paper’s focus on the resource buffer, representing material uncertainty and management. Furthermore, this paper presents a step-by-step process and flow chart for project, construction, and material managers to effectively manage a resource buffer through the CCPM process. This study extends the knowledge of traditional resource buffers in CCPM to improve material and procurement management, thus avoiding the shortage of piping materials and minimizing delays. The resultant process was validated by both deterministic and probabilistic schedule analysis through two case studies of a crude pump unit and propylene compressor installation at a Middle Eastern Refinery Plant Installation. The results show that the CCPM method effectively handles uncertainty, reducing the duration of piping works construction by about a 35% when compared to the traditional method. Furthermore, the results show that, in not considering material uncertainty (resource buffers), projects schedules have the potential for approximately a 5% schedule growth with the accompanying delay charges. The findings have far-reaching applications for both oil and gas and other sectors. This CCPM case-study exemplifies that the material management method represents an opportunity for industry to administrate pipeline installation projects more effectively, eliminate project duration extension, develop schedule-based risk mitigation measures pre-construction, and enable project teams to efficiently manage limited human and material resources.

Highlights

  • Critical Chain Project Management (CCPM) better manages limited essential resources, experienced in recently EPC megaprojects in the middle east Asia. This is illustrated from the following quote, “CPM is as scheduling method to identify the shortest time a project could be accomplished assuming resources are Infinite, whereas CCPM is a method of planning and managing projects that put the main emphasis on the resources required to execute project tasks” This implies that CPM alone does not make sense for field resource allocations and supports this paper’s use of CCPM as a more applicable scheduling analysis tool for EPC megaprojects [30]

  • Through an investigation of scheduling of a crude pump unit and propylene compressor unit, it was found that the traditional PERT/CPM scheduling method may be prone to overestimating project durations (~35% increase of duration when compared to the CCPM method in this study)

  • Excluding material uncertainty in schedule development, a project has a greater potential for schedule growth due to improper risk preparedness (5% schedule growth potential found in this study)

Read more

Summary

EPC Megaprojects Schedule Under-Performance

EPC (Engineering, Procurement, and Construction) megaprojects (>1 billion USD), especially within the petrochemical and oil and gas industries, have experienced substantial cost overrun and prolonged schedule delay. The burden of these overruns and delays fall on the contractor This is most commonly the case in lump-sum turn-key contracts where the EPC contractors manage the contractual liabilities of the project. This paper presents a supplementary procurement management process, including schedule management of the uncertainties, to both fill the research gap and aid practitioners in effectively estimating project schedules. This process was developed for piping installation (one of the major petrochemical and oil and gas activities) and validated through an executed Korean EPC project

Problem Background
Plant Piping Construction
Novelties and Contribution
Relevant Literature
RS1: CCPM Application
RS3: CCPM Incorporating with Material Resource Management
Deterministic Schedule Analysis
Conclusions
Findings
10. Recommendations for Future Research
Full Text
Published version (Free)

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call