Abstract
Activity duration is uncertain due to the variation in the outside environment, such as weather, site congestion, productivity level, etc. Furthermore, resources for construction activities are limited in the real construction world so that scheduling must include resource allocation. A new optimal resource-constrained construction scheduling model is proposed in this paper, in which the effects of both uncertain activity duration and resource constraints are taken into account. Fuzzy set theory is used to model the uncertainties of activity duration. A genetic algorithm-based searching technique is adopted to search for the fuzzy optimal project duration under resource constraints. The model can effectively provide the optimal fuzzy profiles of project duration and resource amounts under the constraint of limited resources.